September 3, 2020 by newturnerpre 0 Comments

132/22kV Substation

MERZ – Talison Greenbushes Lithium Mine

Turners were engaged for the civil package for the construction of the new 132/22kV Substation to service the mine site for recent power upgrades, Turners were responsible for;

  • Clearing & bulk earthworks
  • In ground services and earthing
  • Formwork & concrete works
  • Switchyard Fencing

Date of Completion: March 2019

May 8, 2020 by newturnerpre 0 Comments

Talison Lithium Greenbushes Mondium – TRP

Job Description:

Turners were engaged by Mondium for half of the civil package for the construction of the new Tailings Retreatment Plant at the Talison Lithium Mine Site, Turners works consisted of;

  • Detailed earthworks
  • Supply & installation of reinforcement
  • Highly complex formwork engineering
  • Formwork construction
  • Concrete pumping, placement & finish

Date of Completion: June 2020

July 10, 2019 by newturnerpre 0 Comments

Talison Lithium Greenbushes Water Treatment Plant

Talison – Greenbushes Lithium Mine

Turners were engaged for the civil package for the construction of the new Water Treatment Plant with scope of work consisting of;

  • Detailed earthworks
  • Supply and installation of reinforcement
  • Concrete pumping
  • Formwork
  • Epoxy floor finish to acid areas

Date of Completion: March 2019

July 10, 2019 by newturnerpre 0 Comments

South 32 Boddington Heavy Workshop Floor

South 32 – Boddington Mine

Turners were engaged by South 32 to remove the existing, damaged heavy workshop floor and replace with a new floor, the works consisted of;

  • Concrete cutting & removal of existing concrete floor
  • Earthworks
  • Reinforcement & cast in rail supply & installation
  • Concrete supply, placement & finish
  • Concrete floor & surface hardening

Date of completion: March 2018

July 10, 2019 by newturnerpre 0 Comments

Talison Clearwater Dam Pump Station

Talison – Greenbushes Lithium Mine

Turners were engaged for the concrete civil package for the new clear water dam pump station with scope of work consisting of;

  • Detailed excavation
  • Supply & install detailed reinforcement
  • Formwork
  • Supply, placement and finish of concrete

Date of Completion: August 2018

December 13, 2018 by newturnerpre 0 Comments

Talison CGP1 Conveyor

Specifications of Project

Something here and here and here and here and here and here and here and here and here and here and here and here and here and here and here and here and here and here and here and here and here and here and here and here and here and here and here and here and here and here and here and here and here and here and here and here and here and here and here and here and here and here and here and here and here and here and here.

Something here and here and here and here and here and here and here and here and here and here and here and here and here and here and here and here and here and here and here and here and here and here and here and here and here and here and here and here and here and here and here and here and here and here and here and here and here and here and here and here and here and here and here and here and here and here and here.