Demolish & Dispose of existing concrete floor and construction for a replacement workshop floor.
Specifications of Project
- Supply & Fabrication of all reinforcing steel & embedment
- Supply & Installation of all formwork
- Concrete Supply & Installation - Concrete Pumping - Concrete Place & Finish
Client:
Client Name Pty LtdDate:
July 11, 2019Contact:
BriannaCategory:
CommercialSouth 32 – Boddington Mine
Turners were engaged by South 32 to remove the existing, damaged heavy workshop floor and replace with a new floor, the works consisted of;
- Concrete cutting & removal of existing concrete floor
- Earthworks
- Reinforcement & cast in rail supply & installation
- Concrete supply, placement & finish
- Concrete floor & surface hardening
Date of completion: March 2018